The New York City Planning Commission and the Department of City Planning have adopted two rules that will impact anyone who files land use applications for projects within the City. The new changes go into effect November 14, 2026. What are the Expedited Land Use Review Procedure (ELURP) and the Affordable Housing Appeals Board (AHAB)? We walk you through these voter-approved changes.
What ELURP Is and How It Differs from ULURP
ELURP takes a defined set of modest housing and infrastructure actions out of the City Council’s hands. The review runs 90 days. The community board and borough president simultaneously review the application for 60 days, and the City Planning Commission then has 30 days to hold a hearing and vote to approve, approve with modifications, or disapprove. The Commission’s decision is final.
The notable difference from the Unified Land Use Review Procedure (ULURP) is that the community board and borough president reviews run concurrently. The time each entity has to decide hasn’t changed. Applications certified in June get 90 days, and applications certified from July 1 to July 15 get 75 days.
Which Applications Qualify for ELURP?
The rule covers several categories of action. The one most architects and developers will care about is the zoning map amendment.
For medium- and high-density areas, the district at the time of application must allow residential uses equivalent to R6 or above. The new district can’t increase maximum residential floor area by more than 30%. Where commercial or manufacturing uses aren’t already permitted, they’re capped at 2 FAR.
For low-density areas, the existing district must be R1 through R5 equivalent, and the new district must increase residential capacity. Its standard maximum residential floor area can’t exceed 2.0, and its standard maximum building height can’t exceed 45 feet. The rule uses the Zoning Resolution’s “basic” building height to measure that. It also defines an increase in residential capacity broadly. Added bulk, a newly enabled residential use, or removed required residential parking all count. The same 2 FAR cap on new commercial or manufacturing uses applies.
Beyond rezonings, ELURP covers certain City Map changes, dispositions and acquisitions of City property, site selection for resiliency, solar and open space projects, and Affordable Housing Fast Track applications. Mandatory Inclusionary Housing text amendments can also use the track when they’re proposed alongside an ELURP application. Dispositions to Housing Development Fund Companies (HDFCs) are handled differently. The 90-day timeline stays, but the City Council replaces the Commission in the final 30 days.
Applications Ineligible for ELURP
An application that requires an environmental impact statement can’t use ELURP. Fast Track applications are the exception, and they get 45 days at the Commission instead of 30 when an impact statement is required. Everything else needs a negative declaration or conditional negative declaration before certification.
An ELURP-eligible application filed together with a ULURP application may follow the ULURP process instead. If a rezoning sits close to the 30% line, or if environmental review is likely to be contested, it’s best to determine which track you’re on at the outset of the application process.
The pre-certification clock hasn’t changed
ELURP applications go through the same pre-application and certification process as ULURP applications. The Department has five days for an initial completeness check and 60 days to flag deficiencies. Applicants have 60 days to respond to a request or the application is deemed withdrawn. After 180 days from the Notice of Receipt, an applicant can appeal to the Commission for certification.
Several commenters asked for a shorter pre-certification period. The Department declined to change it in this rulemaking, and said it’s working on separate efforts to speed up pre-certification for both ULURP and ELURP. Fees are the same as ULURP, with no change in amounts. The adopted rule also requires a racial equity report with ELURP applications wherever a ULURP application would need one.
The Affordable Housing Appeals Board
AHAB is a three-member body made up of the Mayor, the Council Speaker, and the affected borough president, or their designees. It’s empowered to reverse certain Council decisions on affordable housing. The Council must have disapproved or modified an application that directly facilitates affordable housing, and the application can’t cover land in two or more boroughs or involve an urban renewal plan.
The timing is tight. The applicant, or two Board members, must request review in writing within five days of the Council’s action. The Board then has 15 days to hold a public meeting and take final action. It can approve an application the Council disapproved, or remove Council modifications and restore the application as the Commission approved it. If the Board doesn’t act, or doesn’t get the required vote, the Council’s decision stands.
Which Applications Qualify for AHAB Review?
An application must facilitate housing and involve or relate to one of the below:
- Application of Mandatory Inclusionary Housing to specified parcels
- Parcels previously made subject to Mandatory Inclusionary Housing
- An Affordable Housing Building
- with a government agency as applicant or co-applicant;
- subject to binding restrictions at the time of approval; or
- with an HDFC as applicant or co-applicant and property owner
A private application that intends to deliver affordable housing, such as one using the Universal Affordability Preference, is ineligible unless it has one of those hooks. If your project depends on AHAB as a backstop, confirm the hook before you file. The Department of City Planning will make a preliminary eligibility determination at certification, but a missed determination doesn’t remove the Board’s power to review.